ShaMaran Q2 2016 Financial and Operating Results

ShaMaran Q2 2016 Financial and Operating Results

August 16, 2016

VANCOUVER, BRITISH COLUMBIA–(Marketwired - Aug. 16, 2016) -ShaMaran Petroleum Corp. (“ShaMaran” or the “Company”) (TSX VENTURE:SNM)(OMX:SNM) is pleased to announce its financial and operating results for the six months ended June 30, 2016. Unless otherwise stated all currency amounts indicated as “$” in this news release are expressed in thousands of United States dollars.

Following the announcement on May 19, 2016 regarding the changed scope of the 31 km long 12” and 36” feeder pipeline from the Atrush block boundary to a tie in point with the main Kurdistan export pipeline (the “Feeder Pipeline”), TAQA Atrush B.V. (“TAQA”), General Exploration Partners, Inc. (“GEP”, a wholly owned subsidiary of ShaMaran) and Marathon Oil KDV BV, have been working very closely with the Kurdistan Regional Government (“KRG”) and KAR Company (“KAR”) regarding a contractual and commercial arrangement for the construction of the Feeder Pipeline.

Commercial and legal discussions are in an advanced state, but proved to be more complex than initially envisaged and have resulted in a delay in the start of construction of the Feeder Pipeline. This will most likely result in first oil to slip into Q1 2017.

Construction and commissioning of the 30,000 bopd Atrush Phase 1 Production Facility (“Production Facility”) is nearing completion. Works are progressing on the 8.5 km section of pipeline being constructed between the Production Facility and block boundary (the “Spur Pipeline”) up to the Feeder Pipeline. The Spur Pipeline is also being constructed by KAR.

The Atrush-4 production well has recently been completed and works are now in progress to complete Atrush-2, the final of four producing wells which will be available for production at startup.

Chris Bruijnzeels, President and CEO of ShaMaran, commented: “Construction of the Atrush production facilities is substantially complete. Following the change in scope for the Feeder Pipeline, all parties involved have been working diligently towards a common goal to get a contractual and commercial arrangement in place to allow construction of the Feeder Pipeline to commence. Unfortunately legal and commercial discussions proved to be more complex and have taken longer than initially envisaged, but are now close to being finalised.”

FINANCIAL AND OPERATING RESULTS FOR THE SIX MONTHS ENDED JUNE 30, 2016

During the reporting period the Company continued its appraisal and development campaign in respect of the Atrush petroleum property located in the Kurdistan Region of Iraq which constitutes the continuing operations of the Company. Atrush currently generates no revenues.

Financial Results

The Company reports a net loss of $5.3 million in the first half of 2016 which was primarily driven by general and administrative expenses, share based payments expense and finance cost, the substantial portion of which was expensed borrowing costs on the Company’s Senior Bonds and Super Senior Bonds. These expenses have been slightly offset by interest income on interest bearing funds as well as service fees.

Condensed Interim Statement of Comprehensive Income 
(Unaudited, expressed in thousands of United States Dollars)

     
  Three months 
ended June 30,
Six months 
ended June 30,
  2016 2015 2016 2015
Continuing Operations

Income
       
Service fees 30 - 30 -
Expenses        
Depreciation and amortisation expense (11) (16) (22) (32)
Share based payments expense (58) (176) (134) (852)
General and administrative expense (1,009) (552) (2,311) (1,515)
Loss before finance items and income tax expense (1,078) (744) (2,467) (2,399)
         
Finance income 12 58 33 546
Finance cost (1,443) (1,370) (2,845) (2,662)
Net finance cost (1,431) (1,312) (2,812) (2,116)
Loss before income tax expense (2,479) (2,056) (5,249) (4,515)
Income tax expense (15) (34) (41) (61)
Loss from continuing operations (2,494) (2,090) (5,290) (4,576)
Discontinued operations        
Net loss from discontinued operations - (4) - (14)
Loss for the period (2,494) (2,094) (5,290) (4,590)
         
Other comprehensive income        
Items that may be reclassified to profit or loss:Currency translation differences 32 42 64 53
Actuarial loss on defined pension plan (505) - (505) -
Total other comprehensive income (473) 42 (441) 53
         
Total comprehensive loss for the period (2,967) (2,052) (5,731) (4,537)
         
 

Condensed Interim Consolidated Balance Sheet 
(Unaudited, expressed in thousands of United States Dollars)

     
  At June 30,
2016
At December 31,
2015
Assets    
Non-current assets    
Property, plant and equipment 201,285 177,044
Intangible assets 89,039 88,645
  290,324 265,689
Current assets    
Cash and cash equivalents, unrestricted 12,186 30,409
Cash and cash equivalents, restricted 16,407 1,512
Other current assets 243 200
  28,836 32,121
Total assets 319,160 297,810
     
Liabilities and equity    
Current liabilities    
Accounts payable and accrued expenses 8,907 9,560
Accrued interest expense on bonds 2,420 2,252
Current tax liabilities 8 31
  11,335 11,843
Non-current liabilities    
Borrowings 155,592 148,263
Provisions 9,687 8,080
Pension liability 2,207 -
  167,486 156,343
Total liabilities 178,821 168,186
Equity    
Share capital 611,179 593,179
Share based payments reserve 6,369 6,235
Cumulative translation adjustment (19) (83)
Accumulated deficit (477,190) (469,707)
Total equity 140,339 129,624
Total liabilities and equity 319,160 297,810
     
 

Total assets increased during the first half of 2016 by $21.3 million which corresponds to increases in share capital by $18 million, borrowings by $7.3 million and other non-current liabilities by $3.8 million which were offset by an increase in the accumulated deficit by $7.3 million, principally due to the net loss recorded in the period, and a decrease in current liabilities by $0.5 million.

Property, plant & equipment assets increased by $24.2 million during the first six months of 2016 was due to $17.9 million of Atrush development costs and capitalised borrowing costs of $6.3 million incurred during the period. The increase in intangible assets by $0.4 million during the first half of 2016 is due to $0.2 million of Atrush exploration costs and capitalised borrowing costs of $0.2 million incurred in the period.

Condensed Interim Consolidated Cash Flow Statement
(Unaudited, expressed in thousands of United States Dollars)

     
  Three months 
ended June 30,
Six months 
ended June 30,
  2016 2015 2016 2015
Operating activities        
Net loss from continuing operations (2,494) (2,090) (5,290) (4,576)
Adjustments for:        
  Interest expense on senior secured bonds - net 1,393 1,307 2,728 2,643
  Share based payments expense 58 176 134 852
  Foreign exchange loss / (gain) 33 54 74 (425)
  Unwinding discount on decommissioning provision 17 - 43 -
  Pension expense 14 - 14 -
  Depreciation and amortisation expense 11 16 22 32
  Interest income (12) (58) (33) (121)
  Changes in provisions - (191) - (267)
  Changes in current tax liabilities (8) (1) (23) (9)
  Changes in other current assets (21) 61 (43) 1,351
  Changes in accounts payable and accrued expenses (3,049) (2,797) (653) (5,277)
Cash used in discontinued operations - - - (8)
Net cash outflows to operating activities (4,058) (3,523) (3,027) (5,805)
         
Investing activities        
Purchases of intangible assets 363 (17,043) 2 (33,367)
Interest received on cash deposits 12 58 33 121
Purchase of property, plant and equipment (8,180) (1) (16,545) (2)
Net cash outflows to investing activities (7,805) (16,986) (16,510) (33,248)
         
Financing activities        
Proceeds on bond issue 17,000 - 17,000 -
Bond transaction costs (780) - (780) -
Shares issued on Rights Offering - - - 60,462
Transaction costs on Rights Offering - - - (1,351)
Interest payments to bondholders - (8,625) - (8,625)
Net cash inflows from / (outflows to) financing activities 16,220 (8,625) 16,220 50,486
         
Effect of exchange rate changes on cash and cash equivalents - (15) (11) 472
         
Change in cash and cash equivalents 4,357 (29,149) (3,328) 11,905
Cash and cash equivalents, beginning of the period 24,236 98,258 31,921 57,204
Cash and cash equivalents, end of the period* 28,593 69,109 28,593 69,109
         
 

The decrease by $3.3 million in the cash position of the Company during the first six months of 2016 was due to cash outflows of $16.5 million on Atrush Block development activities, $2.3 million of cash out on G&A and other cash expenses and $0.7 million of negative cash adjustments from changes in working capital items which were offset by $16.2 million of net proceeds on the issue of Super Senior Bonds.

Operating Results

Production Facility, Export Pipeline and Wells

  • Construction and commissioning of the 30,000 bopd Atrush Phase 1 Production Facility is nearing completion.
  • Work on the Spur Pipeline being constructed between the Production Facility and the block boundary is progressing and is expected to be completed well before the finalisation of the Feeder Pipeline. Construction of the Feeder Pipeline is expected to start shortly. The Atrush partnership, has been working very closely with the KRG and KAR regarding a contractual and commercial arrangement for the construction of the Feeder Pipeline. Commercial and legal discussions are in an advanced state.
  • The completion for the Atrush-4 well has been installed and tested. Work on the Atrush-2 well completion, the final of four producers, has now commenced and is expected to be completed by end August 2016. All four producing wells are now connected to the Production Facility and will be ready for production prior to start-up.

Corporate

  • On February 15, 2016 the Company reported updates to estimated reserves and contingent resources for the Atrush block as of December 31, 2015. Total oil in place is estimated at 1.5 to 2.8 billion barrels, with Total Field Proven plus Probable (“2P”) Reserves on a property gross basis increasing from 61.5 million barrels (“MMbbl”) to 85.1 MMbbl, an increase of 38 percent. Total Field Unrisked Best Estimate Discovered Recoverable Resources (“2P + 2C”)1 on a property gross basis increased from 372 million barrels oil equivalent (MMboe)2 to 389 MMboe.
  • The Company completed a financing arrangement in early May 2016 (the “Financing Arrangement”) with holders of the $140.6 million bonds (the “Senior Bonds”) of General Exploration Partners. Inc., a wholly owned subsidiary of ShaMaran. The Financing Arrangement provides the Company with additional liquidity in 2016 of approximately $33 million based on the issuance of $17 million ($16.2 million proceeds net of transaction costs) of additional super senior bonds (“Super Senior Bonds”) and provides terms for the Company to pay bond coupon interest in kind by issuing additional bonds, including approximately $17.9 million of 2016 coupon interest. Also under the Financing Arrangement the Company issued 218,863,000 common shares at a deemed price of CAD 0.105 per share to holders of the Senior Bonds who elected to convert Senior Bonds into ShaMaran common shares which represented $18 million of Senior Bonds at face value.

1 This estimate of remaining recoverable resources (unrisked) includes contingent resources that have not been adjusted for risk based on the chance of development. It is not an estimate of volumes that may be recovered.

2 Boe may be misleading, particularly if used in isolation. A boe conversion ratio of 6 million cubic feet (“Mcf”) per one barrel is based on an energy equivalency conversion method primarily applicable at the burner tip and does not represent a value equivalency at the wellhead.

ATRUSH OUTLOOK

Production Facility

The construction and commissioning of the 30,000 bopd Atrush Phase 1 Production Facility is substantially complete.

Engineering and design of water injection facilities is planned to commence in 2016 and to continue in 2017.

Oil Export Pipeline

TAQA, as operator of the Atrush PSC, is responsible for the construction of the Spur Pipeline to the block boundary. The construction of the Spur Pipeline is ongoing and is expected to be completed in Q3 2016. The Feeder Pipeline will be owned by the KRG and construction is expected to start shortly under an agreed contractual and commercial arrangement between the Atrush partnership, the KRG and KAR. Commercial and legal discussions are in an advanced state, but delays in the start of construction of the Feeder Pipeline will most likely result in first oil to slip into Q1 2017. Production start is expected once the Feeder Pipeline is commissioned.

Well

Installing the completion of the AT-2 well is expected to be completed by end August 2016. Four producing wells, all equipped with ESPs, will be available for production at start up. This will be followed by the drilling and completion of a dedicated water disposal well and the drilling of an appraisal and development well in 2017.

ABOUT SHAMARAN

ShaMaran Petroleum Corp. is a Kurdistan focused oil development and exploration company with a 26.8% direct interest in the Atrush oil discovery until such time that the Kurdistan Regional Government has completed the exercise of its right to acquire up to a 25% interest. The Atrush Block is currently undergoing an appraisal and development campaign.

ShaMaran is a Canadian oil and gas company listed on the TSX Venture Exchange and the NASDAQ OMX First North Exchange (Stockholm) under the symbol “SNM”. Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. Pareto Securities AB is the Company’s Certified Advisor on NASDAQ OMX First North.

The Company’s condensed interim consolidated financial statements, notes to the financial statements and management’s discussion and analysis have been filed on SEDAR (www.sedar.com) and are also available on the Company’s website (www.shamaranpetroleum.com).

FORWARD LOOKING STATEMENTS

This news release contains statements and information about expected or anticipated future events and financial results that are forward-looking in nature and, as a result, are subject to certain risks and uncertainties, such as legal and political risk, civil unrest, general economic, market and business conditions, the regulatory process and actions, technical issues, new legislation, competitive and general economic factors and conditions, the uncertainties resulting from potential delays or changes in plans, the occurrence of unexpected events and management’s capacity to execute and implement its future plans. Any statements that are contained in this news release that are not statements of historical fact may be deemed to be forward-looking information. Forward-looking information typically contains statements with words such as “may”, “will”, “should”, “expect”, “intend”, “plan”, “anticipate”, “believe”, “estimate”, “projects”, “potential”, “scheduled”, “forecast”, “outlook”, “budget” or the negative of those terms or similar words suggesting future outcomes. The Company cautions readers regarding the reliance placed by them on forward‐looking information as by its nature, it is based on current expectations regarding future events that involve a number of assumptions, inherent risks and uncertainties, which could cause actual results to differ materially from those anticipated by the Company.

Actual results may differ materially from those projected by management. Further, any forward-looking information is made only as of a certain date and the Company undertakes no obligation to update any forward-looking information or statements to reflect events or circumstances after the date on which such statement is made or reflect the occurrence of unanticipated events, except as may be required by applicable securities laws. New factors emerge from time to time, and it is not possible for management of the Company to predict all of these factors and to assess in advance the impact of each such factor on the Company’s business or the extent to which any factor, or combination of factors, may cause actual results to differ materially from those contained in any forward-looking information.

 
Chris Bruijnzeels
President and CEO
ShaMaran Petroleum Corp.
+41 22 560 8605
chris.bruijnzeels@shamaranpetroleum.com

Sophia Shane
Corporate Development
ShaMaran Petroleum Corp.
+1 604 689 7842
sophias@namdo.com
www.shamaranpetroleum.com

Robert Eriksson
Investor Relations, Sweden
ShaMaran Petroleum Corp.
+46 701 112615
reriksson@rive6.ch
Back to top